Suppose a core for a nuclear power plant is installed in year 0 and used for the next five years (years 1- 5). After that it is removed from the plant and stored indefinitely. Beginning in year 6, security for the stored core would cost $200,000 per year. A regulator requires that the plant make a lump sum payment for all future security in year 0 when the core is installed.